Expensive Lessons Learned after 8th Circuit Rules Against Wind Developer in Its $400 Million Suit Against a Minnesota Utility

18 July 2014 Renewable Energy Outlook Blog

Renewable Energy Outlook

A large wind developer, enXco Development Corp. (“enXco”), learned a hard lesson about the importance of negotiating flexibility in contracts to deal with unforeseen regulatory hang-ups, when the U.S. Court of Appeals for the 8th Circuit affirmed a lower court’s ruling to dismiss enXco’s $400 million suit against Northern States Power Co. (“NSP”), a division of Xcel Energy Inc., over its decision to pull out of a 150 MW North Dakota wind deal. A copy of the opinion is available here.

The facts of the case are interesting and bear repeating. NSP originally entered into two contracts with enXco to acquire the wind farm enXco was developing. The first contract was a $15 million purchase and sales agreement for the turbines and real property, and the second contract was a $355 million engineering and construction agreement to construct the project. The purchase and sales agreement contained a number of express conditions precedent, including among other things, that if North Dakota Public Service Commission (“NDPSC”) approvals were not received by a date certain (the “Long-Stop Date”), NSP could terminate its obligations under both contracts. One of the required NDPSC permits was a Certificate of Site Compatibility addressing the project’s effect on endangered migratory birds. However, enXco did not submit this permit application for nearly two years leaving it less than six months to obtain the permit before the Long-Stop Date. Unfortunately, for enXco, a snow storm delayed the permit’s hearing date, and after the hearing was eventually held, NDPSC realized that it had taken place in the wrong county! A new hearing was quickly scheduled, but the 20-day notice requirement meant that it could not take place prior to the Long-Stop Date. NDPSC would not entertain enXco’s request to waive the notice requirement.

NSP brought the hammer down the very next day exercising its contract termination rights because, as the 8th Circuit explains, from the 2008 execution date of the contracts until they were terminated in 2011, the profit margin for wind-energy generation declined to the point that NSP stood to lose significant amounts of money if it chose to proceed with the wind project. enXco sued for breach of contract and NSP moved for summary judgment arguing that its performance under the contract was excused because enXco did not fulfill the purchase and sales agreement conditions precedent. enXco countered that the doctrines of temporary impracticability and disproportionate forfeiture apply to prevent strict enforcement of an “immaterial” condition precedent.

The Circuit Court affirmed the lower court’s decision leaving the parties to their bargain. The doctrine of temporary impracticability did not apply because enXco sat on the NDPSC permit application for approximately two years before submitting it and could have contracted for a more flexible Long-Stop Date. The doctrine of disproportionate forfeiture did not apply because the Long-Stop Date termination clause was express and negotiated among sophisticated parties and enXco retained ownership of the project assets and real estate. NSP walked away with nothing.

The Circuit Court’s opinion was clear and convincing and one wonders why enXco chose to continue to litigate such a weak case in the first place. True NSP’s decision to terminate the contracts was based on a calculated and arguably cynical business decision but had it not walked away its losses would have been pushed down to its ratepayers. enXco on the other hand suffered significant lost profits as compared to actual losses.

The case provides some valuable lessons to EPC contractors and project developers. Anyone reading this decision will be reminded of the importance of consulting regulatory council to review transaction documents prior to closing for potential pitfalls and “gotcha” type termination rights that arise out of unforeseen or uncontrolled events. This case also underscores the need to utilize regulatory council to expeditiously secure all regulatory approvals because when contract terms are clear and unambiguous, the government’s failure to issue a permit in a timely matter will be no excuse in court.

This blog is made available by Foley & Lardner LLP (“Foley” or “the Firm”) for informational purposes only. It is not meant to convey the Firm’s legal position on behalf of any client, nor is it intended to convey specific legal advice. Any opinions expressed in this article do not necessarily reflect the views of Foley & Lardner LLP, its partners, or its clients. Accordingly, do not act upon this information without seeking counsel from a licensed attorney. This blog is not intended to create, and receipt of it does not constitute, an attorney-client relationship. Communicating with Foley through this website by email, blog post, or otherwise, does not create an attorney-client relationship for any legal matter. Therefore, any communication or material you transmit to Foley through this blog, whether by email, blog post or any other manner, will not be treated as confidential or proprietary. The information on this blog is published “AS IS” and is not guaranteed to be complete, accurate, and or up-to-date. Foley makes no representations or warranties of any kind, express or implied, as to the operation or content of the site. Foley expressly disclaims all other guarantees, warranties, conditions and representations of any kind, either express or implied, whether arising under any statute, law, commercial use or otherwise, including implied warranties of merchantability, fitness for a particular purpose, title and non-infringement. In no event shall Foley or any of its partners, officers, employees, agents or affiliates be liable, directly or indirectly, under any theory of law (contract, tort, negligence or otherwise), to you or anyone else, for any claims, losses or damages, direct, indirect special, incidental, punitive or consequential, resulting from or occasioned by the creation, use of or reliance on this site (including information and other content) or any third party websites or the information, resources or material accessed through any such websites. In some jurisdictions, the contents of this blog may be considered Attorney Advertising. If applicable, please note that prior results do not guarantee a similar outcome. Photographs are for dramatization purposes only and may include models. Likenesses do not necessarily imply current client, partnership or employee status.

Related Services

Insights

Do You Know What IMMEX Stands For?
16 July 2019
Dashboard Insights
Does The U.S. Need STRONGER Patents?
16 July 2019
PTAB Trial Insights
California Establishes Fund to Combat Wildfire Threats
15 July 2019
Renewable Energy Outlook
There’s No Place Like Home – But Is That a Reasonable Accommodation?
15 July 2019
Labor & Employment Law Perspectives
Review of 2020 Medicare Changes for Telehealth
11 December 2019
Member Call
2019 NDI Executive Exchange
14-15 November 2019
Chicago, IL
MAGI’s Clinical Research Conference
29 October 2019
Las Vegas, NV
Association for Corporate Counsel Annual Meeting 2019
27-30 October 2019
Phoenix, AZ